Skip to content
OneWorld Solar
Aerial view of the 1.267 MW rooftop solar array OneWorld Solar installed on the Samsonite and TUMI distribution center in Vidalia, Georgia

1.267 MW · Vidalia, Georgia

Samsonite & TUMI: 1.267 MW Rooftop Solar and 55,000 lb of Battery Storage

The largest single installation OneWorld Solar has built: 1.267 MW of rooftop solar over a working distribution center, paired with 55,000 lb of BatteryCube® storage using CATL cells.
System size
1.267 MW
Battery storage
55,000 lb
Cell supplier
CATL
Storage platform
BatteryCube®

The 1 MW solar installation at the Samsonite and TUMI distribution center in Vidalia, Georgia is the largest single system OneWorld Solar has built: 1.267 MW of rooftop photovoltaics across the facility's roof, paired with 55,000 lb of battery storage in BatteryCube® cabinets using CATL cells.

It is also the clearest example of why we treat solar and storage as one design problem rather than two products. The array works on the energy side of the utility bill. The battery works on the demand side. Sizing either one without looking at the other leaves money on the table.

The problem

A distribution center of this size runs a large, steady daytime load — lighting, conditioning, dock equipment, conveyors and compressed air — with a demand profile that the utility bills separately from consumption. Two things followed from that:

  • The roof was a very large asset doing nothing. Distribution centers have the one thing megawatt-scale rooftop solar needs and almost no other commercial building has: acres of uninterrupted, structurally sound roof in a single plane.
  • Reducing kilowatt-hours alone would not fix the bill. As our own financial projections disclaimer puts it plainly, a utility may set a customer's peak demand at a time when solar is not effective — early morning, late afternoon, or during a run of cloudy days. Solar cuts overall usage; it cannot be expected on its own to mitigate peak demand.

The solution

1.267 MW

Rooftop photovoltaic array

Across the distribution center roof.

55,000 lb

Of battery storage

BatteryCube cabinets, CATL cells.

One contract

Full EPC scope

Engineering, procurement, construction, interconnection.

OneWorld Solar delivered the project as a single commercial solar EPC contract: structural and electrical engineering, stamped drawings, the utility interconnection package, procurement, construction, and commissioning.

Rooftop array

The array was laid out to work around the realities of an operating roof — existing rooftop mechanical units, drainage, fire access pathways and the building's structural capacity. The concept rendering issued before construction shows the planned layout; the finished aerial photograph shows how closely it was followed.

BatteryCube storage

The storage sits outdoors on a concrete pad alongside the existing utility transformers, in BatteryCube® cabinets built around CATL cells. Putting the cabinets outside on the load side of the service keeps the battery out of the building's fire-rated envelope and keeps the interconnection short, which matters more on a large system than most people expect: every foot of heavy AC conductor between the storage and the point of interconnection is cost and loss.

Why the battery is not just a bigger array

It is tempting to treat storage as extra solar. It is not. A battery sized to shave a demand peak is usually far smaller than a battery sized to carry a facility through a night, and the two have completely different cost cases. We size storage from the customer's actual interval data, not from the array size. Read more in when commercial battery storage pays off.

The results

OneWorld Solar has not published production or bill-savings figures for this installation. The scope described above is what the company confirms; anything beyond it should come from OneWorld Solar directly.

What can be stated without qualification is the scope: 1.267 MW of rooftop generation and 55,000 lb of battery storage, engineered, procured, built, interconnected and commissioned by one contractor.

Why this project matters for other facilities

If you operate a distribution center, a manufacturing plant or a warehouse in the Southeast, this project is the closest reference point we have. The roof is the asset, the demand charge is usually the problem, and the two need to be solved together.

This system was built in Georgia, where OneWorld Solar is headquartered — 609 Church Street, Vidalia, about as local to this site as a contractor gets.

On site

Photographs from the installation

  • Aerial view of the OneWorld Solar BatteryCube storage bank and utility transformers at the Samsonite and TUMI site in Vidalia, Georgia
    The storage pad sits next to the existing utility transformers, on the load side of the service.
  • OneWorld Solar BatteryCube cabinets containing CATL cells installed on a concrete pad at the Samsonite and TUMI distribution center
    BatteryCube cabinets with CATL cells, branded and assembled by OneWorld Solar.
  • Concept rendering produced by OneWorld Solar showing the planned rooftop solar layout across the Samsonite and TUMI distribution center
    The concept rendering issued before construction.

1 MW solar installation

Frequently asked questions

How big is a 1 MW rooftop solar installation?

A 1 MW rooftop array needs roughly two to three acres of usable roof once you allow for setbacks, fire access pathways, rooftop equipment and shading. That is why megawatt-scale rooftop solar is almost always found on distribution centers, warehouses and manufacturing plants — very few other commercial buildings have that much uninterrupted roof in one place.

Why pair rooftop solar with battery storage on a distribution center?

Solar reduces the energy a facility buys, but it does not reliably reduce peak demand, because the utility can set the peak at a moment when the array is not producing. Storage is what addresses the demand charge. On a large distribution center where demand charges are a substantial share of the bill, the battery is often working on a different line of the invoice than the panels.

Can solar be installed on a working distribution center without shutting it down?

Yes. Rooftop work happens above an operating building, so the constraint is coordination rather than shutdown: dock scheduling, crane and material lifts, roof loading limits and the electrical tie-in window. The tie-in is the only part that normally needs an outage, and it is usually planned for a weekend or a scheduled maintenance period.

What are BatteryCube cabinets?

BatteryCube® is OneWorld Solar's own branded commercial battery energy storage cabinet line, built around CATL cells. At the Samsonite and TUMI site the cabinets sit outdoors on a concrete pad next to the utility transformers. You can read the full specification on the BatteryCube product page.

Related

Similar projects and reading

Want a system like the one at Samsonite / TUMI Luggage?

Send twelve months of utility bills and we will come back with a system size, an installed cost, the incentives you can apply for and a payback range.