Santee Cooper large load rate: what it means for a South Carolina business
Santee Cooper's published rate schedules now include an experimental large load schedule that is mandatory for data centers above 50,000 kW and for portable loads above 1,000 kW. For the ordinary South Carolina business on the general service rate, the number that matters is still the $12.21 per kW demand charge, and there is something to do about it.
4 min read